|   | 
		  
			
			  
			 We have budgeted capital expenditures 
			  in 2004 of approximately $45.0 million, of which $39.8 million is 
			  expected to be used for drilling activities in our project areas 
			  and the balance is expected to be used to fund 3-D seismic surveys, 
			  land acquisitions and capitalized interest and overhead costs. We 
			  have budgeted to drill approximately 35 gross wells (14.3 net) in 
			  the Gulf Coast region and 13 gross wells (9.4 net) in our East Texas 
			  area and Barnett Shale trend in 2004. We expect to obtain a mezzanine 
			  project facility to finance a majority our acquisition, exploration 
			  and development program in the Barnett Shale trend in 2004. Assuming 
			  we are successful in obtaining this facility, our capital expenditures 
			  in the trend could be between $20 and $30 million in 2004. The actual 
			  number of wells drilled and capital expended is dependent upon available 
			  financing, cash flow, availability and cost of drilling rigs, land 
			  and partner issues and other factors.  
			We have continued to reinvest a substantial 
			  portion of our cash flows into increasing our 3-D prospect portfolio, 
			  improving our 3-D seismic interpretation technology and funding 
			  our drilling program. Oil and gas capital expenditures were $38.2 
			  million, $26.7 million and $33.4 million for 2001, 2002 and 2003, 
			  respectively. Our drilling efforts resulted in the successful completion 
			  of 20 gross wells (5.9 net) in 2001, 17 gross wells (6.0 net) in 
			  2002 and 35 gross wells (9.4 net) in 2003 in the Gulf Coast region. 
			  Of the 77 gross wells (29.0 net) drilled or acquired by CCBM, a 
			  majority have been contributed to Pinnacle.  
			CCBM spent $4.6 million for drilling costs 
			  through December 2003, 50% of which would be spent pursuant to an 
			  obligation to fund $2.5 million of drilling costs on behalf of RMG. 
			  Through December 31, 2003, CCBM has satisfied $2.3 million of its 
			  drilling obligations on behalf of RMG. Pinnacle has reported that 
			  it drilled 124 gross wells during the second half of 2003 and completed 
			  just under half of them by year-end 2003. Pinnacle reportedly added 
			  approximately 10.0 Bcf of net proved reserves through development 
			  drilling through December 31, 2003. Its gross operated production 
			  has increased by approximately 70% since its inception (to approximately 
			  8.2 MMcf/d), and its total well count stands at 369 gross operated 
			  wells, according to Pinnacle.  
			FINANCING ARRANGEMENTS  
			Hibernia Credit Facility  
			On May 24, 2002, we entered into a credit 
			  agreement with Hibernia National Bank (the "Hibernia Facility") 
			  which matures on January 31, 2005, and repaid our existing facility 
			  with Compass Bank (the "Compass Facility"). The Hibernia Facility 
			  provides a revolving line of credit of up to $30.0 million. It is 
			  secured by substantially all of our assets and is guaranteed by 
			  our subsidiary.  
			The borrowing base will be determined 
			  by Hibernia National Bank at least semi-annually on each October 
			  31 and April 30. The initial borrowing base was $12.0 million, and 
			  the borrowing base as of January 31, 2004 was $16.0 million. Each 
			  party to the credit agreement can request one unscheduled borrowing 
			  base determination subsequent to each scheduled determination. The 
			  borrowing base will at all times equal the borrowing base most recently 
			  determined by Hibernia National Bank, less quarterly borrowing base 
			  reductions required subsequent to such determination. Hibernia National 
			  Bank will reset the borrowing base amount at each scheduled and 
			  each unscheduled borrowing base determination date.  
			On December 12, 2002, we entered into 
			  an Amended and Restated Credit Agreement with Hibernia National 
			  Bank that provided additional availability under the Hibernia Facility 
			  in the amount of $2.5 million which is structured as an additional 
			  "Facility B" under the Hibernia Facility. As such, the total borrowing 
			  base under the Hibernia Facility as of December 31, 2002 and 2003 
			  was $15.5 million and $19.0 million, respectively, of which $8.5 
			  and $7.0 million, respectively, were drawn as of such dates. The 
			  Facility B bore interest at LIBOR plus 3.375%, was secured by certain 
			  leases and working interests in oil and natural gas wells and matured 
			  on April 30, 2003. We used proceeds from our offering in February 
			  2004 to repay the outstanding balance under the Hibernia Facility. 
			  As of March 29, 2004, no amounts were drawn under the Hibernia Facility. 
			 
			  
			31  
			
		   | 
		    |